# Scheme Work Name Year NIT / NIQ & Work Order Amount Area / Block Progress Beneficiaries Agency Status
451
PMGSY / MAINTENANCE OF RURAL ROADS
Previous
Construction of PMGSY road from Gokarna to Asoalampur
2017-18 — — Kandi
Phys0
Fin0.00000
0 — —
452
Transport / Safe Drive Safe Life Equipment Distribution
Previous
Supply of life Jackets, life Buoya, life buoya with light and life line , air filled/foam floating rubber tubes with string, Installation of public address system, sypply of fire extinguisher, nine litre mechanical foam and supply of fire bucket with stamp for 50 nos. Ferry ghat in Murshidabad district
2017-18 — — All Blocks
Phys100
Fin67.0898
— — Completed
453
Transport / Infrastructure Development
Previous
Construction of Passenger waiting facility with toilet (Ordinary Swatch Bharat Model) for ladies and Gents including Ticket Counter & store room adjacent to/along with Jetty Ghat Grill Gate door with Locking Facility including Electrification (10 nos. Ferry Ghat)
2017-18 — — All Blocks
Phys100
Fin45.96717
— — Completed
454
Transport / Infrastructure Development
Previous
Arrangement of Driking water (siking of DWP tube well) in 10 nos. Ferry Ghat of Murshidabad District.
2017-18 — — All Blocks
Phys100
Fin4.97332
— — Completed
455
Transport / Infrastructure Development
Previous
Supply & Installation of CCTV with 4 nos camera for 50 nos. Ferry Ghat of Murshidabad District.
2017-18 — — All Blocks
Phys80 CC TV
Fin13.98008
500000 ZP Ongoing
456
Transport / Infrastructure Development
Previous
Construction of Sand Box at 10 nos. Ferry Ghat of Murshidabad District.
2017-18 — — All Blocks
Phys100
Fin0.51778
— — Completed
457
Transport / Lightening of Roads/Bridges
Previous
Installation of Compound light for 10 nos. Ferry Ghat of Murshidabad District.
2017-18 — — All Blocks
Phys100
Fin4.9949
— — Completed
458
Transport / Lightening of Roads/Bridges
Previous
Installation of Signage for implementation of SOP at 10 nos. Ferry Ghat of Murshidabad District.
2017-18 — — All Blocks
Phys100
Fin9.46086
— — Completed
459
Transport / Lightening of Roads/Bridges
Previous
Installation of Navigation light for 2 nos. Ferry Ghat & boats in Murshidabad District.
2017-18 — — All Blocks
Phys100
Fin1.99576
— — Completed
460
NRHM / Construction/Maintenance of PHC/BPHC/RH/Dist. Hopital
Previous
MOHAMMADPUR PHC (PART WORK)
2017-18 — — RAGHUNATHGANJ - II
Phys100
Fin6.84
47000 ZP Completed
461
NRHM / Construction/Maintenance of PHC/BPHC/RH/Dist. Hopital
Previous
PANCHTHUPI PHC (RENOVATION WORK)
2017-18 — — BURWAN
Phys100
Fin4.20
51000 ZP Completed
462
NRHM / Insfrustrature Maintenance
Previous
OPERATION & MAINTENANCE OF PWSS
2017-18 — — RANINAGAR - II, JALANGI, LALGOLA, KHARGRAM, BURWAN, NABAGRAM, KANDI
Phys100
Fin104.84
120000 BDO/PS Completed
463
NRHM / Sinking of Tubewell
Previous
SINKING COST OF TUBEWELL
2017-18 — — ALL BLOCK
Phys100
Fin146.94
7000000 BDO/PS Completed
464
Own Fund / Morrum/Concrete Road const.
Previous
Construction of Cement Concrete Road starting from Gopalnagar Kashem SK. House at Gopalnagar village at Hizole GP under Kandi Block.
2017-18 — — Kandi
Phys100%
Fin5
— RMC, Murshidabad Completed
465
Own Fund / Morrum/Concrete Road const.
Previous
Construction of road prtective Wall at Nischantapur Bhangla pond under Mahula-2 GP under Beldanga-I Block.
2017-18 — — Beldanga-I
Phys100%
Fin1.64
— RMC, Murshidabad Completed
466
Own Fund / Morrum/Concrete Road const.
Previous
Construction of Cement Concrete Road stating from Khosbaspur Baro Culvert to Khosbuspur Pry. School at Gokarna-II GP under Kandi Block.
2017-18 — — Kandi
Phys100%
Fin0
— RMC, Murshidabad Completed
467
Own Fund / Morrum/Concrete Road const.
Previous
Constration Of Cement Concrete Road From Dhiren Hazra house towards union Bank at Kundal under Kalyanpur-II GP in Burwan Block, Msd (Chanage 219 m to 435m.)
2017-18 — — Burwan
Phys100%
Fin1.659
— RMC, Murshidabad Completed
468
Own Fund / Morrum/Concrete Road const.
Previous
Balance work of construction of Two nos. changing room with toilet facility at Basia under Guru Pasla GP in Nabagram Block
2017-18 — — Nabagram
Phys100%
Fin0
— RMC, Murshidabad Completed
469
Own Fund / Morrum/Concrete Road const.
Previous
Improvement of Cement Concrete Road Starting from Saspara Main Road at Ajay SK house at Andula GP under Kandi Block.
2017-18 — — Kandi
Phys100%
Fin5
— RMC, Murshidabad Completed
470
PMAY(G) / Construction of Dwelling Houses
Previous
Cosntruction Dwelling Houses (44241 nos.)
2017-18 — — All Blocks
Phys44039 in nos.
Fin52831.20
44241 BDO/PS Ongoing
471
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction black top road from M/S K.R Indian Gas Godown to Dighi in Mahalandi GP & Kumarsanda GP in Kandi Block & Construction of black top road starting from Jibanti Sherpur State Highway near Mahalandi Haqueshed Shop to M/S K.R Indian Godown in Mahalandi GP under Kandi Block
2017-18 — — Kandi
Phys100%
Fin61.00739
— ZP —
472
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of cement road starting from Harinagar Kabarsthan to Harinagar Pry.School at Harinagar under Hizole GP in Kandi Block
2017-18 — — Kandi
Phys100%
Fin28.52188
— ZP —
473
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of concrete road from Gangapur Seru Sk's house towards Manjur Sk house and Ganga Talmandha pond towards Munjun Sk's house and Gangapur Talmandha Pond towards Ear Ali house under Beldnaga-I Block
2017-18 — — Beldanga-I
Phys100%
Fin16.77613
— ZP —
474
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Cement Concrete Road from the Mahisasthali Culvart to the end of Mahisasthali village
2017-18 — — B-Gola-I
PhysWIP
Fin0
— ZP —
475
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Cement Concrete Road from the Baharagachi to the Fulandar Primary School at Gaginagar Malancha GP
2017-18 — — Samserganj
Phys100%
Fin36.71503
— ZP —
476
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Cement concrete road from taldanga kalimandir towards Tapan Roy house via house of Beauty Singha Roy at Taldanga under Saktipur G.P.
2017-18 — — Beldanga-II
Phys100%
Fin16.98127
— ZP —
477
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of guard wall beside Rahamat Karigar's house and road at Patkabari Amir Mondal house to Damdama Faizuddin Master house under Nowda Block
2017-18 — — Nowda
Phys100%
Fin40.95378
— ZP —
478
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of concrete road from Kodalkati Nijamuddin Biswas house to Abdul Bari Mondal's house under Nowda
2017-18 — — Nowda
Phys100%
Fin26.93864
— ZP —
479
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Cement concrete road from Choa Madhob halder House to Choa Khaspara Sadar Sk house under Choa GP under Hariharpara Block.
2017-18 — — Hariharpara
Phys100%
Fin13.40016
— ZP —
480
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Box culvert and concrete road from Kanchannagar house of Delsad Sk to Kaman Sk at Beharia GP in Hariharpara Block
2017-18 — — Hariharpara
Phys100%
Fin26.64383
— ZP —
481
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Concrete road from bank of Pradip Danga Dighi's pitch rasta to Humayun Jakir Sk's house under Hariharpara Block
2017-18 — — Hariharpara
Phys100%
Fin12.63134
— ZP —
482
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of black top road from Ranipur towards Saidpara via Rayhat under Sahora GP in Burwan PS & Construction of black top road from Saidapur towards Ranipur via Rayhat under Sahora GP in Burwan PS
2017-18 — — Burwan
Phys100%
Fin85.48176
— ZP —
483
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of cement concrete road from Jumma masjit to Hazipara village at Azmali delear via Jumma masjit to Dakshinpara under Bannyeswar GP in Sagardighi Block
2017-18 — — Sagardighi
Phys100%
Fin29.10928
— ZP —
484
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of cement concrete road from Telandighi pitch rasta to Fulban pitch rasta under Sagardighi GP in Sagardighi Block (Phase-I) & Construction of cement concrete road from Telandighi pitch rasta to Fulban pitch rasta under Sagardighi GP in Sagardighi Block (Phase-II)
2017-18 — — Sagardighi
Phys100%
Fin57.63692
— ZP —
485
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of concrete road from Loknathpur Uttarpara Kader Ali Mollah house Foizole Mallick house plot no-762 under Sompara-I GP in Beldanga-II Block
2017-18 — — Beldanga-II
Phys100%
Fin12.8094
— ZP —
486
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of cement concrete road from Anando Halder house to Sardarpara road under Rampara-I GP in Beldanga-II Block
2017-18 — — Beldanga-II
Phys100%
Fin6.40047
— ZP —
487
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of cement concrete road from Politapara Mannan Farazi house to Aiyub Nabi house under Sompara-I GP in Beldanga-II Block
2017-18 — — Beldanga-II
Phys100%
Fin8.72519
— ZP —
488
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of High drain from Boliharpara Chandromohon pukur towards Rentu Sk Grill factory & Boliharpara eid haha moidane to Sukur Ali Sk houseunder Sompara-I GP in Beldanga-II Block (Phase-I)
2017-18 — — Beldanga-II
Phys100%
Fin14.71571
— ZP —
489
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Reparing of black top road from Bansabati Raj Bonsi para to Sarbasri Ghat (Hilora) under Bangsabati GP in Suti-I Block (Phase-I) & Reparing of black top road from Bansabati Raj Bonsi para to Sarbasri Ghat (Hilora) under Bangsabati GP in Suti-I Block (Phase-II)
2017-18 — — Suti-I
Phys100%
Fin60.38821
— ZP —
490
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of concrete road from K.B Road Ramdova Bus-Stand to Ramdova MSK 1No (3.00M) span culvert at Suti-I Block (Phase-I) & Construction of concrete road from K.B Road Ramdova Bus-Stand to Ramdova MSK 1No (3.00M) span culvert at Suti-I Block (Phase-II)
2017-18 — — Suti-I
Phys100%
Fin65.76903
— ZP —
491
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of concrete road at Mirzapur under Raghunathganj-I Block
2017-18 — — Raghunathgani-I
Phys100%
Fin25.49685
— ZP —
492
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Renovation of road from NH-34 to AligarCamp& Ahiran Police outpost under Suti-I Block
2017-18 — — Suti-I
Phys100%
Fin19.15361
— ZP —
493
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of KB road to Gaighata to Pancgachi Ferry ghat under Harua GP in Suti-I Block (Phase-I) & Construction of KB road to Gaighata to Pancgachi Ferry ghat under Harua GP in Suti-I Block (Phase-II) and Construction of cement concrete road from house of Mortuz Sk to Pancgachi Ferry ghat via Idgah under Harua GP in Suti-I Block
2017-18 — — Suti-I
Phys100%
Fin73.04482
— ZP —
494
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Black top road from Kedarnath Bridge to Nishindra Ferry Ghat under Farakka Block (Phase-I) Construction of Black top road from Kedarnath Bridge to Nishindra Ferry Ghat under Farakka Block (Phase-II)
2017-18 — — Farakka
Phys100%
Fin50.5032
— ZP —
495
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of road from Sahadiar school more towards puratan canal under Garaimari GP in Domkal Block & Construction of road from puratan canal towards Karbala Maharamtala under Garaimari GP in Domkal Block and Construction of road from Maharamtal Karbala towards Nikhal Mia & Hakim Dr's house under Garaimari GP in Domkal Block
2017-18 — — Domkal
Phys100%
Fin87.49742
— ZP —
496
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of Box culvert and concrete road road from Momin Sk house towards NH-34 road under Radhaghat-I GP in Berhampore Block
2017-18 — — Berhampore
Phys100%
Fin26.45626
— ZP —
497
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of road from Barianagar Singar Bagan more towards Dakshinsahar Jumma Masjid under Saralpur GP in B-Gola-II Block & Construction of road from Dakshinsahar Jumma Masjid towards Diarapara under Saralpur GP in B-Gola-II Block
2017-18 — — B-Gola-II
Phys100%
Fin62.71236
— ZP —
498
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of cement concrete road from Jorgacha culvert to Ayub Nabi house at Betberia under Chaintnyapur-I GP under Beldanga-I Block
2017-18 — — Beldanga-I
Phys—
Fin0
— ZP —
499
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of PCC road from Lal Mallick house towards Abol bepari house at Khagru para old Sarak under Mirzapur-I GP in Beldanga-I Block
2017-18 — — Beldanga-I
Phys100%
Fin24.58316
— ZP —
500
Non-RIDF/Non-PMGSY / Road and Culvert Maintenance
Previous
Construction of PCC road from Dihipara Jafar Sk's house towards PMSGY road at Mahula-I GP under Beldanga-I Block
2017-18 — — Beldanga-I
Phys100%
Fin8.75283
— ZP —
Showing 451–500 of 1,080